U.S. 42 closure set for June 11-15

Posted by akiefaber June 8th, 2012, 1:39 pm Post a Comment

As part of the U.S. 42 widening project, culvert work will require the closure of a portion of U.S. 42 next week, according to the Ohio Department of Transportation.

The closure will be in place between Cox Road and Tylersville Road, just north of the entrances to the Pisgah Youth Park baseball fields, 9116 Columbus-Cincinnati Road, and the West Chester Nursing and Rehabilitation Center, 9117 Columbus-Cincinnati Road.

The closure will begin Monday, June 11 and is scheduled to be completed by 5 p.m., Friday, June 15 with U.S. 42 reopened to traffic at this time.

Northbound U.S. 42 traffic will be detoured north to Cox Road to east on Tylersville Road to U.S. 42. Southbound traffic will be detoured west to Tylersville Road to south on Cox Road to U.S. 42.

Access to all addresses will be maintained with addresses north of 9117 Cincinnati-Columbus Road accessible from Tylersville Road and addresses south of and including 9117 accessible from Cox Road.

Arrow boards and/or signs will be in place prior to the work zone to alert motorists of the upcoming road closure. To help ensure the safety of the construction workers as well as the traveling public, motorists should remain alert, reduce their speed and watch for stopped traffic.

The completion date for the entire U.S. 42 project is June 2013. The project includes widening U.S. 42 to three lanes. The widening area will provide a through lane in each direction and a middle two-way left-turn lane, from Fields-Ertel Road north to Butler-Warren Road. It also includes left turn lanes on both approaches of Dimmick Road.

Crews hope to have all major items completed by Dec. 2012 with the exception of surface course asphalt, final striping and final grade/landscaping.

West Chester Township offers a monthly construction update meeting for property owners in the impacted area. The meetings are held the first Wednesday of the month at 7:30 a.m. in Township Hall, 9113 Cincinnati-Dayton Road. Updates are also available on the township’s website www.WestChesterOH.org. The next meeting will be held July 11 due to Independence Day falling on the first Wednesday of July.

no comments yet

Posted in: News |

Tags: Tags: , , , , , , , , , , ,

MonNov21

U.S. 42 widening project remains on schedule

Posted by akiefaber November 21st, 2011, 3:00 pm Post a Comment

According to a press release from West Chester Township, the U.S. 42 widening project remains on schedule. The completion date for the entire project is June 2013.

Currently, all subcontractors are progressing northward with the curb placement and the asphalt placement between Dimmick Road and West Chester Road.

It is still the goal of Ohio Department of Transportation and the contractors to complete this part of the project before Dec. 1.

Over the winter months, crews will address drainage on the east side between Fields-Ertel and West Chester Road, and on the north end of the project from West Chester Road to Butler Warren.

A very tentative look ahead to 2012/2013 is to have all major items completed by Dec. 2012 with the exception of surface course asphalt, final striping and final grade/landscaping.

Weather conditions will impact schedule.

While the construction continues, businesses on U.S. 42 will remain open.

West Chester Township offers a monthly construction update meeting for property owners in the impacted area. The meetings are held the first Wednesday of the month at 7:30 a.m. in Township Hall, 9113 Cincinnati-Dayton Road. Updates are also available on the township’s website www.WestChesterOH.org.

Water main work on West Chester Road: Butler County has begun work to replace a water main on West Chester Road between John Road and Barret Road. Traffic on West Chester Road is being maintained throughout the project, with the exception of an anticipated one-day closure to complete the project. The replacement project will take approximately 90 days, weather permitting.

Accident cleared up: Allen Road between Union Centre and Muhlhauser road re-opened around noon Monday after a traffic accident caused damage to a utility pole.

no comments yet

Posted in: News, Traffic |

Tags: Tags: , , , , , , , , , , ,

Connect with WestChesterBuzz

Subscribe

Get community news delivered straight to your inbox.

Featured Businesses

Send us Photos

  • Attach a JPEG (.jpg) photo to your story. Maximum file size is 4 MB.
  • Add a caption, include names & communities of people pictured. (Caption limit: 500 characters, including spaces)

Recent Photos

ohsoftball9 ohsoftball3 ohsoftball1 ohsoftball6 ohsoftball7 ohsoftball4 ohsoftball2 ohsoftball10 bn teen crash season 11
View more photos >